Coordination Table (Local & USA Parts)

Key Points

The Coordination Table ( Local & USA Parts ) is a document that affirms the ability of the supplier to confirm deliver date of products for new design change that NMEX requirements .

The Coordination Table ( Local & USA Parts ) document should be prepare by NMEX and submit to Supplier in order to confirm the adoption timing and delivery parts date with new design change and replay back to NMEX prior agreement between them in order to avoid obsolete or high cost inventory.

Minimum Content Requirements

A separate Coordination Table ( Local & USA Parts ) shall be raised for

A new Coordination Table ( Local & USA Parts ) shall be raised following the introduction of new Design Change during mass production stage.

Document Description

Coordination Table (Local).

No. Item Completion Instructions
1 Consecutivo Nissan internal control number
2 Fecha Issued Date
3 Proveedor Supplier Name
4 Atencion Supplier Engineer in Charge
5 Do Note Design Change Number
6 Dossier Devolution Design Change Number (Only Renault)
7 Modelo Model Code involved
8 Tipo De Cambio Change Description
9 Parte Importante Part Importance
10 Tabla Part Number detail and quantity
11 Respuesta Due date replay confirmation form Supplier
12 Observaciones Notes from NMEX
13 Tabla Part Number detail and quantity form Supplier
14 Descripción De Tabla Part Number detail and quantity form Supplier
15 Observaciones Notes and Signed Off form Supplier

Coordination Table (USA Parts). SUPPLIER CHECK LIST TO DETERMINE PALNNED ADOPTION DATE Details to be
completed

No. Item Completion Instructions
1 Supplier name Name of supplier involved
2 Design Note No. Design Note number
3 Drawing Receipt Date: Date of drawing received by supplier
4 Design .Note Receipt date: Date of Do Note received by supplier
5 Part Number (s) Part number involved
6 Drawing or Shape # / level Level of Drawing N, 1, 2, etc.
7 Content of change: Change or modification detail
8 Tier 2 involvement Sub supplier involved
9 Lead time New modification manufacturing time
10 Supplier Testing Internal Testing development
11 Purchasing orders for tool and parts. Purchasing orders issued by Nissan
12 Tool modification/build time Dates of start and end of tool modification
13 Samples submission Date of sample delivery at Nissan
14 Functional Result from Nissan & PSW Sign off Sample part confirmation Result and official announce from Nissan to supplier and Parts approval PSW signed off.
15 Timing Trial timing of parts
16 Exhaust inventory of old level part Parts Inventory of old condition
17 Planned adoption date (@ NMEX) Implementation Timing
18 Supplier Comments Notes from supplier
19 Nissan Approvals: Signed off from Nissan
20 Supplier Commitment: Signed off from supplier
21 Nissan Internal Use: Nissan additional comments
22 Nissan Internal Use: Nissan additional comments